Builders on site: the client’s checklist, before, during and after
If your business is having an extension, a new unit or a refit done at its own premises, CDM 2015 makes you the client, and the Fire Safety Order still makes you responsible for getting everyone out. This is one sheet of what usually needs doing, each line with the regulation or guidance it comes from.
One A4 sheet. Free, with no form to fill in. General information for England and Wales, not legal advice.
Building work at our site: client checklist
1. Before work starts
- ☐If more than one contractor will work on the project, or it is reasonably foreseeable that there will be, a principal designer and a principal contractor are appointed in writingCDM reg 5(1)
- ☐Pre-construction information sent to every designer and contractor: what you already hold, such as drawings, an existing health and safety file and your asbestos survey or registerCDM reg 4(4)
- ☐A construction phase plan exists before the construction phase begins, drawn up by the contractor (one contractor) or the principal contractorCDM reg 4(5)(a)
- ☐Welfare facilities for the builders are arranged: toilets, washing, drinking water, somewhere to rest and changeCDM reg 4(2)(b), Sch 2
- ☐Notifiable? More than 30 working days with more than 20 workers at once, or more than 500 person days. If so, the client notifies HSE in writing before the construction phase beginsCDM reg 6
- ☐Fire risk assessment reviewed for the works: escape routes, alarm coverage and the assembly point while part of the site is a building siteFire Safety Order art 9(3)
- ☐Who controls which part of the premises, and when, is agreed with the contractor, and how you will co-ordinate fire precautionsFire Safety Order art 22
2. While the builders are on site
- ☐Every contractor signs in and out, so your roll call includes them on day one, not after the first drillGood practice
- ☐Contractors are told about your site’s risks and rules before they start (a record of who was told what is how you show it)MHSW Regs reg 12(1), (3)
- ☐Method statements and risk assessments are received, read and filed for each trade before its work startsGood practice
- ☐Hot work (welding, grinding, cutting, torch-on roofing) only under a written permit, with a fire watch afterwards; check your insurer’s hot work conditionInsurer, FPA RC7
- ☐Escape routes, fire doors and final exits are not blocked or locked by the works, and any change to the route is briefed to staffGOV.UK evacuation plan
- ☐If the assembly point moves for the build, everyone, including the contractors, is told where it is nowGOV.UK evacuation plan
- ☐The arrangements are kept under review as the project moves on, not set once at the startCDM reg 4(3)
3. At handover
- ☐If more than one contractor worked on it: health and safety file received from the principal designer (or the principal contractor, if there is no principal designer), and kept where the next person to work on the building can find itCDM reg 4(5)(b), 12(10)
- ☐New building, extension or change of use: fire safety information handed over by whoever did the work, and your notice acknowledging it signed and returnedBuilding Regs reg 38
- ☐Fire risk assessment reviewed again for the finished building, and the review recordedFire Safety Order art 9(3), (6)
- ☐A timed drill in the finished layout, with the roll call taken from whatever list you will rely on in a real fireGOV.UK drills guidance
General information about published law and guidance, England and Wales, not legal advice. Sources and full wording: noonelite.com/cdm-client-checklist.
Being straight with you
What this sheet does not do
- This is general information about published law and guidance, not legal or health and safety advice. Your own risk assessments, your principal designer and principal contractor, and your insurer decide what applies to your project.
- It covers England and Wales. Scotland and Northern Ireland have their own fire safety law. The building regulation 38 handover notice applies in England from 1 October 2023 and in Wales from 1 July 2026.
- Domestic clients are treated differently under CDM 2015. This sheet is written for a business having work done at its own premises.
- Method statements and risk assessments from contractors are marked “good practice” because no regulation uses those words for the client. They are how most sites show they did what regulation 4 asks.
- We are not CDM advisers, principal designers or fire risk assessors. We make visitor and contractor sign-in kiosks, which is why the sign-in line is on the sheet.
The three CDM roles, in the regulations’ own wordsA hot work permit you can printA contractor induction recordWhen the work is finished: moving into the new space
Sources
Check any of this yourself
- Construction (Design and Management) Regulations 2015, regulation 4Client duties: arrangements, pre-construction information, the construction phase plan and the health and safety file.
- CDM 2015, regulation 5 and Schedule 2When a principal designer and principal contractor must be appointed in writing; Schedule 2 lists the welfare facilities.
- CDM 2015, regulation 12Paragraph (10): who passes the health and safety file to the client at the end.
- CDM 2015, regulation 6When a project is notifiable, and that the client gives the notice.
- HSE, commercial clients: roles and responsibilitiesHSE’s own summary for businesses having work done.
- Regulatory Reform (Fire Safety) Order 2005, article 9Review of the fire risk assessment when premises “undergo significant changes, extensions, or conversions”, and the record of it.
- Fire Safety Order, article 22Co-operation and co-ordination where more than one responsible person has duties in respect of the premises, “whether on a temporary or a permanent basis”.
- Building Regulations 2010, regulation 38Fire safety information at completion, and the acknowledgement notice (England and Wales).
- Management of Health and Safety at Work Regulations 1999, regulation 12Information for the employer of anyone working in your undertaking (12(1)), and “appropriate instructions and comprehensible information” for the person themselves (12(3)).
- HSE, the duty to manage asbestosWhat the asbestos register is, and who holds the duty.
- GOV.UK, fire safety and evacuation plansEscape routes, exits and a safe meeting point.
- GOV.UK, fire safety equipment, drills and trainingAt least one fire drill a year, results recorded.
Read on legislation.gov.uk and GOV.UK on 9 November 2026, latest available text.
Before you ask
Questions clients ask about CDM
Am I the client under CDM 2015 if the builder runs the job?
Regulation 2(1) defines the client as “any person for whom a project is carried out”, and HSE’s guidance L153 says the regulations apply in full to commercial clients. Appointing a principal contractor moves a lot of the work to them, but regulation 4 keeps duties with you, including making suitable arrangements, providing pre-construction information and making sure the construction phase plan exists before work starts. The long version is on our page about construction work at your site.
When does a project have to be notified to HSE?
Regulation 6(1) says a project is notifiable if the construction work is scheduled to “last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project; or exceed 500 person days.” Where it is, regulation 6(2) puts the duty on the client to give notice in writing to HSE “as soon as is practicable before the construction phase begins”. HSE’s online F10 form is how most clients do it.
What is the fire safety information under regulation 38?
In England and Wales, where building work erects or extends a relevant building or comes with a relevant change of use, regulation 38 of the Building Regulations 2010 requires the person carrying out the work to give fire safety information to the responsible person. The responsible person must now also give back a notice (in England since 1 October 2023, in Wales since 1 July 2026) acknowledging receipt and confirming the information is enough to understand, operate and maintain the building and its fire safety systems. If you have not been asked to sign one, ask your builder.
Also asked of sites like yours
The other things somebody may ask you to evidence
Each of these is a page about one standard, one duty or one visitor, written the same way as this one: what it actually asks for, what an iPad at reception records towards it, and where it does not help.
- GDPR and the visitor book
- CMMC physical security
- List X visitor control
- ITAR visitor log
- Def Stan 05-138 visitor access
- ISO 27001 visitor access
- PCI DSS visitor log
- Forensic science code visitor record
- AEO visitor access control
- Known consignor visitor control
- CTPAT visitor log
- TISAX visitor management
- TAPA FSR visitor log
- BRCGS visitor control
- BRCGS packaging visitor control
- BRCGS storage and distribution visitors
- BRCGS unannounced audit
- Visitor control non-conformity
- SALSA visitor control
- IFS Food visitor hygiene
- UFAS feed mill visitor control
- GMP visitors in production areas
- GDP wholesale visitor control
- Fire roll call
- Contractor management
- Mortuary visitor and contractor record
- Construction work in occupied premises
- HSE inspection records
- ISO 45001 contractor control
- Visitor NDA sign in
- Visitor record retention
- What a visitor log must contain
- Standards calendar
- Sign in sheet template
- Visitor health questionnaire template
- Contractor induction template
- Permit to work template
- Hot work permit template
- Fire drill record template
- Moving into new premises checklist
- First 90 days site safety checklist
If it helps
Contractors signing in on day one
Fifteen minutes on the phone if you want to see how the kiosk signs contractors in and puts them on the live roll call while the build is on. If the sheet and a paper book are doing the job, keep using them.
Book a 15 minute callWe will say so on the call.
Would rather email? [email protected]